产品介绍: 1、Type of construction2、Technical Index   ClassificationProject NameTechnical IndexDamping   coatingThe flammability test of the surfaceComply with IMO 2010 FTP Code Part 5The flue gas and toxicity testComply with IMO 2010 FTP Code Part 2Rock   Wool SlabDensity140kg/m3±5NoninflammabilityComply with IMO 2010 FTP Code Part 1Steel   Wire MeshSpecificationThe Specification is 150X150mm ,Ø5Deck   CoveringDensity≤1200kg/m3FluidityΦ≥130mmBreaking   Strength≥3.5MPaCompressive   Strength≥10MPaThe flammability test of the surfaceComply with IMO 2010 FTP Code Part 5Integral   StructureFire   ResistanceComply with IMO 2010 FTP Code Part 5Sound   Insulation Index≥45dBWeight   per unit area≤87.95kg/m2 3、The performance characteristicsThe refractory deck has good floating performance, and can effectively reduce the noise and vibration noise.This deck is applicable to high-demanding sound insulation shipping space. 4、Fire resistance ratingThe flammability of the surface:Comply with the 1974 SOLAS IMO 2010 FTP Code Part 5. 5、Recognised classification societyDNV.GL 、CCS 、EC 6、Packaging and dosage (per square metre to calculate)Serial No.Mterial NamePacking SpecificationDosage1Rock Wool Slab140kg/m3   1200X600X50.0mm1.4piece2Steel Wire MeshØ5,1500X2000mm0.33piece3AC-JII Refractory Deck Covering25kg/bag2.72bag4DP-SDI Damping coating20kg/barrel0.01barrel 7、Construction technology  7.1 The steel deck need be rust-protect treatment,it is no oil pollution,dust and other contaminants on the surface;  7.2 Brush the DP-SDI Damping coating on the steel deck;  7.3 Using pumping machine to pump or dump the deck covering which mixed on the damping,use a foam roller to remove the air bubbles in the deck covering, and promote the flow of the deck covering ;  7.4 After the DP-SDI Damping coating curing,lay the rock wool slab and the Flat-fell seam tight, leaving no space;  7.5 Lay the steel wire mesh on the rock wool slab,fixed the joint.  7.6 Paste a circle of surrounding edge blue bar on the steel casing;  7.7 Using pumping machine to pump or dump the deck covering which mixed on the steel wire mesh,use a foam roller to remove the air bubbles in the deck covering, and promote the flow of the deck covering ;  7.8 After the deck covering curing,hook out of the surrounding edge article blue and filled with rock wool; 8、Note  8.1 After mixing,the deck covering must be finished laying within one hour, if manually stirring must be stirring evenly;  8.2 During the deck covering construction and curing, the environmental temperature should be in 10 ~ 35 ° C.When the temperature above 35 ℃ cooling measures should be taken;When the temperature lower 0 ℃  heat preservation measures should be taken;  8.3 The deck covering should be moistureproof, prevent bask in, and stored in a ventilation environment.Material shelf life is 6 months;  8.4 Lay the rock wool after the bottom of the deck covering (about 12 hours) curing;  8.5 Lay the Rock ,try to keep it flat-fell seam.
Features: The refractory deck has good floating performance, and can effectively reduce the noise and vibration noise.This deck is applicable to high-demanding sound insulation shipping space.
Fire rating: The flammability of the surface:Comply with the 1974 SOLAS IMO 2010 FTP Code Part 5.
Parameter DNV.GL 、CCS 、EC
颜色:
注意事项:

1 After mixing,the deck covering must be finished laying within one hour, if manually stirring must be stirring evenly;

2 During the deck covering construction and curing, the environmental temperature should be in 10 ~ 35 ° C.When the temperature above 35 ℃ cooling measures should be taken;When the temperature lower 0 ℃  heat preservation measures should be taken;

3 The deck covering should be moistureproof, prevent bask in, and stored in a ventilation environment.Material shelf life is 6 months;

4 Lay the rock wool after the bottom of the deck covering (about 12 hours) curing;

5 Lay the Rock ,try to keep it flat-fell seam.

 

  • Details
  • Precautions
  • Features

 

1、Type of construction

QQ截图20151208002850.png

2、Technical Index

  

Classification

Project Name

Technical Index

Damping   coating

The flammability test of the surface

Comply with IMO 2010 FTP Code Part 5

The flue gas and toxicity test

Comply with IMO 2010 FTP Code Part 2

Rock   Wool Slab

Density

140kg/m3±5

Noninflammability

Comply with IMO 2010 FTP Code Part 1

Steel   Wire Mesh

Specification

The Specification is 150X150mm ,Ø5

Deck   Covering

Density

≤1200kg/m3

Fluidity

Φ≥130mm

Breaking   Strength

≥3.5MPa

Compressive   Strength

≥10MPa

The flammability test of the surface

Comply with IMO 2010 FTP Code Part 5

Integral   Structure

Fire   Resistance

Comply with IMO 2010 FTP Code Part 5

Sound   Insulation Index

≥45dB

Weight   per unit area

≤87.95kg/m2

 

3、The performance characteristics

The refractory deck has good floating performance, and can effectively reduce the noise and vibration noise.This deck is applicable to high-demanding sound insulation shipping space.

 

4、Fire resistance rating

The flammability of the surface:Comply with the 1974 SOLAS IMO 2010 FTP Code Part 5.

 

5、Recognised classification society

DNV.GL 、CCS 、EC

 

6、Packaging and dosage (per square metre to calculate)

Serial No.

Mterial Name

Packing Specification

Dosage

1

Rock Wool Slab

140kg/m3   1200X600X50.0mm

1.4piece

2

Steel Wire Mesh

Ø5,1500X2000mm

0.33piece

3

AC-JII Refractory Deck Covering

25kg/bag

2.72bag

4

DP-SDI Damping coating

20kg/barrel

0.01barrel

 

7、Construction technology

  7.1 The steel deck need be rust-protect treatment,it is no oil pollution,dust and other contaminants on the surface;

  7.2 Brush the DP-SDI Damping coating on the steel deck;

  7.3 Using pumping machine to pump or dump the deck covering which mixed on the damping,use a foam roller to remove the air bubbles in the deck covering, and promote the flow of the deck covering ;

  7.4 After the DP-SDI Damping coating curing,lay the rock wool slab and the Flat-fell seam tight, leaving no space;

  7.5 Lay the steel wire mesh on the rock wool slab,fixed the joint.

  7.6 Paste a circle of surrounding edge blue bar on the steel casing;

  7.7 Using pumping machine to pump or dump the deck covering which mixed on the steel wire mesh,use a foam roller to remove the air bubbles in the deck covering, and promote the flow of the deck covering ;

  7.8 After the deck covering curing,hook out of the surrounding edge article blue and filled with rock wool;

 

8、Note

  8.1 After mixing,the deck covering must be finished laying within one hour, if manually stirring must be stirring evenly;

  8.2 During the deck covering construction and curing, the environmental temperature should be in 10 ~ 35 ° C.When the temperature above 35 ℃ cooling measures should be taken;When the temperature lower 0 ℃  heat preservation measures should be taken;

  8.3 The deck covering should be moistureproof, prevent bask in, and stored in a ventilation environment.Material shelf life is 6 months;

  8.4 Lay the rock wool after the bottom of the deck covering (about 12 hours) curing;

  8.5 Lay the Rock ,try to keep it flat-fell seam.

 


1 After mixing,the deck covering must be finished laying within one hour, if manually stirring must be stirring evenly;

2 During the deck covering construction and curing, the environmental temperature should be in 10 ~ 35 ° C.When the temperature above 35 ℃ cooling measures should be taken;When the temperature lower 0 ℃  heat preservation measures should be taken;

3 The deck covering should be moistureproof, prevent bask in, and stored in a ventilation environment.Material shelf life is 6 months;

4 Lay the rock wool after the bottom of the deck covering (about 12 hours) curing;